I have the following questions regarding Tasks using Tasks List
- I used to be able to sort the activities manually by using ALT+ arrow up or down. Has that been removed or am I missing a step? I cant seem to be able to organize the activites unles I am sorting by a column. but we dont want that. We want to be able to sort however we want and be able to move the tasks up or down after created.
- Is there a way to remove slack? I want to be able to create hand offs but I don't want the system to calculate or add slack. This is extremely annoying as it changes the dates we are trying to set.