Planned Purchase Order not viewed by the MRP
Hi
We want to use planner purchase order to schedule the receiving of component based on the discrete job requirement
In our simulation, the demand is coming from a sales order with several request date
Line | Ordered Item | Qty | Unit Selling Price | Internal Item | UOM | Status | Request Date | Promise Date |
---|---|---|---|---|---|---|---|---|
1.1 | SA018147R00100 | 2 | 31'600.00 | SA018147R00100 | Pce | Entered | 03.02.2025 | 03.03.2025 |
1.2 | SA018147R00100 | 2 | 31'600.00 | SA018147R00100 | Pce | Entered | 10.02.2025 | 10.03.2025 |
1.3 | SA018147R00100 | 2 | 31'600.00 | SA018147R00100 | Pce | Entered | 17.02.2025 | 17.03.2025 |
1.4 | SA018147R00100 | 2 | 31'600.00 | SA018147R00100 | Pce | Entered | 24.02.2025 | 24.03.2025 |
1.5 | SA018147R00100 | 2 | 31'600.00 | SA018147R00100 | Pce | Entered | 03.03.2025 | 31.03.2025 |
1.6 | SA018147R00100 | 2 | 31'600.00 | SA018147R00100 | Pce | Entered | 10.03.2025 | 07.04.2025 |
1.7 | SA018147R00100 | 2 | 31'600.00 | SA018147R00100 | Pce | Entered | 17.03.2025 | 14.04.2025 |
Based on the Fixed Days Supply parameter, we are able to release one requisition for the entire quantity needed for the component required in the entire sales order