How to Adjust revenue for wip cost of sales and goods?

edited Mar 7, 2025 9:26AM in Projects - EBS (MOSC) 1 commentAnswered

In wip cost of sales and goods is 400000. 1st progressive payment certified for 30% 365000.

Using percent complete method revenue is generated for cost incurred. the remaining 35000 should be in wip. it should come in revenue for the next time. how to adjust revenue?

Provide me the answer for this scenario in oracle ebs.