Value Chain Planning - EBS (MOSC)

MOSC Banner

Setup To Offloading Operation To An Alternate Resource When Primary Resource Is Not Available

edited Apr 12, 2025 3:51AM in Value Chain Planning - EBS (MOSC) 4 commentsAnswered

Production Scheduling (PS)

What to do setup to Offloading Operation To An Alternate Resource When Primary Resource Is Not Available?

An operation is setup with primary (P1) and alternate (A1) resources. The primary resource (P1) has a downtime event during the planning horizon and is not available for scheduling.

— Haresh

Tagged:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center