Resource requirements are not showing in ASCP for EAM work orders with 'Calculate Resource Req' enab
Resource requirements are not showing in ASCP for EAM work orders with 'Calculate Resource Req' enabled - In EBS, wwe have an ASCP Plan that is configured to
- Enforce capacity constraints
- Calculate resource requirements
After collecting data and launching the plan, on planning workbench —> tools —> Resources, the requirements are all blank - no data is there. In Availability form, we can see the details.
Any idea why the Resource requirements for maintenance work orders are not displayed in ASCP?