Hyperion EPM System Patching Process

We are preparing to upgrade from Hyperion EPM 11.2.15 to Hyperion EPM 11.2.21. The deployment consists of 5 Windows servers. The configuration of the servers is as follows:

Server 1: Foundation server (Calc Mgr, HFR, HP, HFS, Essbase and HRMI).

Server 2: Foundation server (Calc Mgr, HFR, HP, HFS, Essbase and HRMI).

Server 3: HFM and FDMEE.

Server 4: HFM and FDMEE,

Server 5: Essbase.

In the past when upgrading the organization chose to apply Hyperion updates patches in serial in the following order:

Server 1 apply update patches waiting for completion of the patching process.

Then patch

Server 2 apply update patches waiting for completion of the patching process.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center