Is there a way for BLU to be displayed in a converted unit on the Resource Usage Profile?
After setting up resources to be linked to the budgeted labor hours in the schedules, I have obtained an output similar to the Activity Usage Profile in P6 with the Resource Usage Profile.
It shows the amount of budgeted hours across multiple projects, this is great!
What I would like to know is if there is a way for me to get the graph/histogram in the schedule module to display these labor hours in different units. Specifically instead of showing the raw count of hours in a given week that we have to work to accommodate the hours input on an activity, I'd like to display the amount of staff we need to accommodate those hours instead.