Resource Hour Allocation Exceeds Max Units Per Time When Using a Resource Curve

in Primavera (MOSC) 2 commentsAnswered

Hello all,

I assigned a resource curve - and was very surprised to find the hourly allocation for the day to be over the resource limit of 8h/d. Also - the curve is even through the first 70% of its duration, but the amount allocated is higher during the first day.

Note the 13 hours on Monday, then the 9 hours Tue - Mon.

Here is the resource's information that is assigned to the activity:

And here is the curve:

The activity is Task Dependent, Fixed Duration and Units, % Complete - Duration. The calendar is a standard 8h/day - M-F.

I'm at a loss to explain why there are more hours allocated than the resource's 8h/d limit.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center