Actuals become 0 when Activity is updated 100%
Hello All,
I have imported the Actuals via XLS import , My Activities are updated without an issue when my Duration type is Fixed Duration and Units and it shows the Budgeted and Actuals as per data updated in Xls.
But when i set the Duration Type is fixed Units , while importing the progress from XL template all in-progress activity % it shows correctly Units % value and Actual units are updated correctly. if Activity is progressed 100 % then it shows Units % completion is 0 and Actual units are 0 . But Actual Duration is showing as per consumption.
not sure it is a Bug or any one is experencing this problem. kindly suggested if any fix is available to solve this issue.