Hi,
I am manufacturing two finished products (Product A and Product B).
To manufacture these two finished products, I use a semi-finished product (Product C).
When I run program R3483, it generates two Planned Work Orders (WO) for Products A and B to meet the forecast demand. It is also generating two Planned Work Orders (WO) for Product C.
QUESTION: Can I make R3483 generate only one Planned Work Order for Product C?
Version: 9.2
Tools: 9.2.8.3
Best regards,