Unconstrained Plan not respecting Lead Time
Hi
We are implementing OPM-Unconstrained ASCP.
This is the planning horizontal plan:
This is the lead time information of the item:
Item | Org | BOM Item Type | Pegging | Preprocessing LT | Processing LT | Postproc. LT | Fixed LT | Variable LT | Fixed Order Qty | Fixed Lot Mult. | Min Ord Qty | Max Ord Qty | Minimum Shelf Life Days | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
PM-CB-00028 | UJA:MPR | Standard | End Assembly/Soft Pegging | 3 | 17 | 7 | 17 | 0 | 2400 | 2400 |
Why the lead time not respected? In my opinion, the planned order should be released before 1 sep 2025.
Thank you
Aji