Value Chain Planning - EBS (MOSC)

MOSC Banner

Unconstrained Plan not respecting Lead Time

Hi

We are implementing OPM-Unconstrained ASCP.

This is the planning horizontal plan:

This is the lead time information of the item:

Item

Org

BOM Item Type

Pegging

Preprocessing LT

Processing LT

Postproc. LT

Fixed LT

Variable LT

Fixed Order Qty

Fixed Lot Mult.

Min Ord Qty

Max Ord Qty

Minimum Shelf Life Days

PM-CB-00028

UJA:MPR

Standard

End Assembly/Soft Pegging

3

17

7

17

0

2400

2400

Why the lead time not respected? In my opinion, the planned order should be released before 1 sep 2025.

Thank you

Aji

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center