Why Schedule % Complete is not updated at the WBS level
Al realizar la ejecución del programa, no se actualiza el Schedule % Complete y Performance % Complete a nivel de WBS, a pesar de que las actividades relacionadas a estos si cuenten con valores diferentes a 0% en estos campos. Ya he cargado una Línea Base original sobre la cual se analiza el valor ganado. He probado recalculando costos y sigue sin mostrar estos campos actualizados.
Ayuda por favor.
Saludos.
Translated by Admin:
When you run the program, the Schedule % Complete and Performance % Complete are not updated at the WBS level, even though the activities related to the Schedule % Complete and Performance % Complete are not updated with values other than 0% in these fields. I have already uploaded an original Baseline on which earned value is analyzed. I have tried recalculating costs and still do not display these updated fields.