OM Schedule Ship Date not updating after WIP Job Completion Date changes (ATP data not refreshed)

Hello,

  • I have a sales order line for an item that needs to be manufactured (Make-to-Order)
  • The item has an ATP rule assigned and valid transit times are maintained
  • When I create the order, the system calculated e.g.:
    • Request Date: October 22
    • Schedule Ship Date: October 17
    • Schedule Arrival Date: October 22
  • Later, the related WIP Job (linked to the sales order line) was updated — the completion date changed to October 20.

However, even after:

  • running “Schedule Order Lines” concurrent request,
  • manually re-scheduling the line from the sales order form,
  • and confirming that the ATP rule is assigned to the item,

…the Schedule Ship Date in Order Management still does not update based on the new completion date from WIP.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center