P6 "Copy Activity Options" the Resource is Checked but not included in newly copied Proj why?
“Copy Activity Options” feature when copying an existing project. that the “Resource & Role Assignments” is already ticked as checked. But still not including the “Resource & Role Assignments” for the new copied
Project. the resources and roles that should be included are already tagged as Global.