P6 Data Dictionary mistakes?

in Primavera (MOSC) 1 commentAnswered

In the P6 data dictionary, you are defining the "Forecast at Completion" as the "estimated cost at completion":

But checked the formulas and I believe this is the VAC (Variance At Completion) VAC = BAC - EAC!

Am I wrong or there is a mistake?

Sounds corroborated by an other field definition:

Thanks for your clarification.

Best,

Olivier