OPC - Schedule Scenarios - WBS
Hey There,
I've built a what if schedule, based on another what if schedule, and I've added new WBS elements to help breakdown all of the new tasks, but when I try to assign or see the WBS(so not hiding unused WBS) they never show up. Is the WBS for Scenarios based on the Parent/Current Schedule? and there isn't a separate WBS for each Scenario?
Edit:The Scenario status seems automatically set to closed and it's not editable. I created the 1st scenario based on the Initial Baseline(so maybe 3 months ago - and there've been weekly updates) Is this why it's happening?