Hi,
We are having 2 different schedules with external relationship linking both the schedule. We want to merge the schedule in OPC as single project to run risk analysis. But there is no reliable way to copy WBS from both the schedule without renaming activity ID and without affecting the external relationship. Can anyone help us with the steps on how to merge it into single schedule?