End item has Component A usage 4 per assembly effective for Unit K005 to K009.

Created MDS entry for 4 units Unit K005 and see planned order generated for 16 units of Component A

Now disabled Component A in BOM for End Item

Added Component B qty 4 per assembly effective for K005 to K009

Ran MRP. Plan generates planned order for both Component A and component B. We expect plan order to be generated for Component B only as Component A was disabled.