Impact of switching from local to global ASL for supplier-specific lead times in ASCP
We use Oracle ASCP for material planning. For some purchased items, our sourcing rules assign multiple suppliers to the same item, and each supplier has a different processing lead time. However, we can maintain only one processing lead time per item in the item master.
We are using local Approved Supplier List (ASL) entries. We found that global ASL entries allow us to maintain a different processing lead time for each supplier.
Before switching from local to global ASL entries for these items, we would like to clarify two points:
- Will ASCP use the processing lead time for the supplier selected by the sourcing rule instead of the lead time defined in the item master?