We are currently implementing SuitePeople, and have run into an issue with the work calendars. First some background:
- Employees normally work Monday-Friday
- Occasionally employees will be required to work over the weekend.
- We schedule our project in NetSuite using project tasks, and project task assignments
The issue we ran into a few years ago was that if an employee's work calendar was set to M-F, and they were to be assigned to a project task that was scheduled on the weekend, the assignment would fail with the following message:
At least one employee assigned to the task Weekend Work has no working hours between the start date 8/14/2021 and end date 8/15/2021.
As we were not using work calendars for anything important, we simply set the default calendar to Sunday-Saturday.
Now with the implementation of SuitePeople, work calendars are suddenly very important in ensuring that vacation requests only use vacation days for working days. We need to go back to a M-F work calendar, but can't due to errors in the project task assignments. Is this something that people have run into before, and is there a way to suppress the task assignment error mentioned above?
Thanks,
-Sandy