How to prevent MRP Planned order consolidation of supply for different Demand orders?
Our customer would like to have the Transfer orders created grouped by the demand orders.
This is the situation: Aluminiumcan250ml is a component in 2 Assemblies.
For a workorder for assembly 1 there are 30 units of Item A needed
For a workorder fto build assembly 2 there are 36 units of Item A needed
When the supply planning has run a planned order, type Transfer order, is created based on the Planning rule group for a correct quantity 66.
Our customer would prefer to have 2 transfer orders created for the same item with the same TO and FROM locations:
1 transfer order for 30 units
1 transfer order for 36 units