Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Update your Profile with your Support type to get your Support Type badge.
Expand your NetSuite knowledge by joining our Ask A Guru Live sessions. RSVP on this event now.
Make Your Voice Heard: What Tech & ERP Topics Should We Explore in our Next Webinar?? We’re all ears! Vote now, and the poll runs until January. Poll for ERP | Poll for Tech.
Uncover the power of data with the Analytics Hub —your ultimate guide to mastering NetSuite Saved Searches and Reports. Simplify the complex and unlock your organization's true potential. Dive into the Analytics Hub now and soar to new heights!
SuiteWorld 2025 registration is officially OPEN
SuiteWorld is the largest annual gathering of the NetSuite community! It will be held in Las Vegas on October 6-9, 2025. Our customers and partners look forward to SuiteWorld every year as a place to hear the latest from NetSuite, get hands-on learning, and connect with each other. Register now!
SuiteWorld is the largest annual gathering of the NetSuite community! It will be held in Las Vegas on October 6-9, 2025. Our customers and partners look forward to SuiteWorld every year as a place to hear the latest from NetSuite, get hands-on learning, and connect with each other. Register now!
SuiteAnswers will undergo an upgrade on May 13, 2025 05:30 UTC. During this time, the system may be unavailable for up to 4 hours. Please submit your cases via NetSuite Account Center or via call if urgent.
Supply allocation date logic
Hello,
I am trying to understand the logic NS uses for determining the expected ship date on work orders linked to sales orders.
I have a sales order with at Expected Ship Date and Supply Required by Date of 6/9/24
On the work order I have the following dates.
Supply Required by Date of 6/9/24
Expected Supply Date 9/8/24 (non late items)
Production Start Date 1/8/24 (forward scheduling)
Planned Component Issue Date (1/8/24 or as in line with routing)
How is it that the expected supply date is later than the production start date? If I change the Supply Required Date to 1/8/24 then the Supply Required Date moves to 4/7/24. What is the calculation that is being performed to determined these dates?
Tagged: