Project value changed
Hi guru's,
Question about the projected value on the Work Order Completion.
On friday I created a work order completion (with backflush). To my great surprise, the projected value is calculated based on the average cost of the component and not based on the selected Lot numbered price.
- Component: Average cost €60
- Component: Lot numbered cost €20
After the weekend I looked again at the same work order completion and I see that the projected value now uses the price of the Lot (€20) (and not the average(€60)). In the System notes I see that a script has been running at 7:00 PM that performs a recalculation based on the cost method of the inventory item.