Our goal as a construction company is to automate recognizing portions of project expenses in the period of their related revenue, so we can follow the accounting matching principle. We invoice (revenue) customers at 33%, 66%, and 100% project completion. Since there can be many material and labor bills, we want to avoid preparing huge JEs.
The NetSuite Help Center has an article on "Using Percent-Complete Amortization for Project," which is exactly what we're looking for. I tried following all the instructions in our sandbox, but the test amortization schedule remains in the status of "not started" no matter what I try.
Here's a detailed breakdown of what I've done:
We already had the amortization feature enabled.
I created a variable amortization template.
It has "straight-line, by even periods" as the default method. "Transaction date" as the default term source. Deferral account is our Deferred Expense account. Default target account. Everything else is blank.
I created/approved a test bill tied to a project.
In the expenses subtab, I have a material expense account. I selected the variable amortization template.
Once done, it created the "AS27" schedule. The GL impact is Dr. Deferred Expense Cr. A/P, as expected.
Lastly, I created a project task and time tracking to have a non-0% work complete.
After creating those, in the project overview it shows 100.0% for "percent work complete."
I've tried it with "Use System Percentage of Completion for Schedules" in accounting preferences checked and un-checked.
I verified that AS27 isn't listed on the "Create Amortization Journal Entries" page.
I verified that the time tracking is in approved status.