Discussions
Join us for complimentary one-day events around the world and step into a future fueled by AI and limitless potential. Explore new breakthroughs, sharpen your skills, and connect with experts who are shaping what’s next. Experience bold keynotes, interactive learning, and connections that span the global NetSuite community. Discover what's next at SuiteConnect Tour 2026.
We’re excited to announce that the 2025 Community Recap is now available! This special recap highlights the amazing contributions and achievements of our members over the year and celebrates the collective success of our community.
Check your personalized recap to see the impact you made in 2025 and how your efforts helped shape our community’s growth and success.
View Your 2025 Community Recap
Thank you to everyone for your passion, collaboration, and support. Here’s to building an even stronger community together in the year ahead!
Season’s greetings to you and yours! As we head into the holidays (December 24 – January 4), we want to take a moment to celebrate the incredible strength and collaboration within our community. Even during the break, you can continue to benefit from connecting with peers, searching related threads, posting your questions, and marking helpful replies as “Accepted” in the Support Community.
Please note our dedicated team will be on reduced coverage during this time, and regular responsiveness will resume on January 5. Wishing you a joyful and restful holiday season!
-The NetSuite Support Community Team
Why is Planning Workbench not suggesting transfers from warehouse to production location?
Hello,
We have recently moved inventory into an outside warehouse with the idea that NS via MRP in the Supply Planning Workbench would suggest transfer orders when safety stock levels were hit. For example
Total quantity on hand for Item A is 100
10 @ production location
90 @ warehouse location
Saftey stock level is 50.
I would expect MRP to suggest a planned transfer order of 40 from the Warehouse to the production location. That is not happening. Instead MRP is suggesting a PO for Item A.
In speaking with a NS ACS they suggested enabling Distribution networks, I did that but it appears the item replenishment methods must be set for time-phased in order for that to work.. We use MRP. Can any one help me out with this one as I'm stumped now. Seems crazy that MRP wouldn't suggest planned transfer orders from an outside warehouse.