What is the normal behavior of the Production End Date when using Backward Scheduling Method?
Hi Guru's,
Questions, when a Work Order with Schedeling Method 'Backwards' is changed to the status 'In Process' the production end date will change, based on the production start date.
For example, I create a work order with an production end date of 17-02-2023. When I Release my work order the date stays 17-02-2023.
When I do a work order completion and the status of the work order changes to In Process the Production end date is changed to the day of the completion.
Is this normal behavior of NetSuite?
For our customer, this end date may absolutely NOT change due to a status change.