Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
How to setup fixed Run Time in Manufacturing Routing?
Run Time associated with a work center in manufacturing routing only depends on quantities of the work order: we cannot handle fixed machine run time.
To understand the issue, the following is a use case that is practically found on any chemical company that has mixing operations.
In fact, mixing machines have a fixed setup time (setup time) given by the loading and flushing of the machine and a machine run time (always fixed, e.g., 1 hour for a single operation).
How would this situation be manageable with the current Manufacturing Routing record structure? I have only one fixed time field available. This obviously acts incorrectly on the costing of the operation.