We are evaluating the Outsourced Manufacturing feature for use case described below and have a fundamental question on how to setup and configure the items
Use Case: Raw Steel is purchased from Vendor 1 using standard PO; shipped to and received at Outsource Mfg Vendor A. Outsource Mfg Vendor A provides cut/stamp service and ships resulting product to Outsource Mfg Vendor B. Outsource Vendor B provides hardening service and ships resulting product to company manufacturing location to build out finished good product for sale
Question: Should items be setup as follows? Or is there a different configuration that facilitates roll up of the costs to final Finished Goods item?
Inventory Items to include Raw Steel purchased from Vendor 1, plus any other purchased items included as components in final Finished Good BOM
Three Assembly Items with corresponding BOM records to include
- Resulting product from Outsource Mfg Vendor A "SubAssembly A"
- Resulting product from Outsource Vendor B "SubAssembly B", which would include SubAssembly A as a component
- Final Finished Goods assembly which would include SubAssembly B as a component
Service for Purchase or Other Charge for Purchase items for the Outsourced Mfg Vendor costs. One for each Oursourced Mfg Vendors A and B