Discussions
Stay up-to-date with the latest news from NetSuite. You’ll be in the know about how to connect with peers and take your business to new heights at our virtual, in-person, on demand events, and much more.
Now is the time to ask your NetSuite-savvy friends and colleagues to join the NetSuite Support Community! Refer now! Click here to watch and learn more!
Stay in the Know
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Be sure you're subscribed to NetSuite communication to stay in the know about monthly happenings, updates and announcements. Subscribe
Supply allocation date logic
Hello,
I am trying to understand the logic NS uses for determining the expected ship date on work orders linked to sales orders.
I have a sales order with at Expected Ship Date and Supply Required by Date of 6/9/24
On the work order I have the following dates.
Supply Required by Date of 6/9/24
Expected Supply Date 9/8/24 (non late items)
Production Start Date 1/8/24 (forward scheduling)
Planned Component Issue Date (1/8/24 or as in line with routing)
How is it that the expected supply date is later than the production start date? If I change the Supply Required Date to 1/8/24 then the Supply Required Date moves to 4/7/24. What is the calculation that is being performed to determined these dates?