MRP does not create suggestion planned order for current month Item Demand Plan
Hi Gurus,
I have created an Item Demand Plan with the following details:
- Start Date: 23 Feb 2025, End Date: 01 Mar 2025, Quantity: 300
- Start Date: 02 Mar 2025, End Date: 08 Mar 2025, Quantity: 500
I ran the MRP Repository, but the system did not suggest a Planned Order for the 300 quantity in February or March 2025, although it did generate a suggestion for the 500 quantity. Is this how the NS standard works, where the system does not account for the first day of the starting month?
Additionally, I have not configured settings for Planning Fences, Safety Stock, Purchase Lead Time, and the Supply Sizing Lot is set to "Lot for Lot."