Item-Organization to Organization assignment - GOP scheduling logic
Summary:
All,
We have a scenario where Ship-From warehouse on a sales order line/fulfill line is passed manually - not determined by the Global Sourcing rules.
However, there are local sourcing rules to determine the sources of supplies (other warehouses); if the Ship-From warehouse on the sales order line/fulfill line does not have enough quantity.
The sourcing rules and the assignments are defined as below.
Here is the scenario:
- Sales order line is for qty 50 with Ship-From warehouse = B and req date in 5 days.
- B has no qty available and no supplies like PO or TO to promise against.
0