Issuing Project Striped material to a work order
Hello,
I have a question. I have received material quantities striped (Linked) to a project.
Whenever I try to issue these material in a work order I get an error that tells me I have zero quantity and negative balance is not allowed.
Given that the work order I am trying to issue material in is linked to the same project/task?
So can we issue material to a work order and this material is linked/striped to a project?
0