Production Calendar Exceptions in Redwood unexpected behaviour
Summary:
We are having unexpected behaviour in Production Calendar Exceptions. Our calendar goes from Monday to Thursday. We added an exception to add a shift on 7/18, Friday. Then we added an exception to delete a shift on 7/17, Thursday. After hitting save and returning to the month view of the calendar. The exception on Friday no longer shows and has moved over to 7/17. The exception on 7/17 doesn't show at all. This only happens in the Redwood UI. In the standard UI it works correctly.
Content (please ensure you mask any confidential information):
We tested adding an exception to add a shift on Sunday 7/27 and then an exception to delete the shift on 7/28. This shows correctly in both Redwood UI and the standard UI. We named the exceptions after their day of the week, so we could track them better.