Configuration Migration from Test to PROD
Summary: We have our application live with HCM since last 2 year and CRM which went live 2 months back. Parallel we have P2P implementation going on which might go-live down the line 6-8 months.
P2P is on DEV.
CRM Support is from TEST
Now considering the above setup, the additional changes we are receiving on the CRM front are being migrated using CSM but every now and then we face issues on our Live application considering the all the configuration from TEST gets copied to PROD. Below are few of the issues we are facing.
- We have PaaS components which are enabled on HCM application using page integration, while doing CSM activities all the links starts point to test as per test configuration.