Work Centers with override calendars error out in Lead-time calculation
Summary:
We have override calendars on two work centers and get an error when running the Calculate Lead-time report.
Content (please ensure you mask any confidential information):
Here is the error we receive: The lead time calculation was not performed for item xxxxxx because there is a processing error. Check the log file for details. There is nothing in the log file but our parameters. If the work definition doesn't contain one of these work centers, the program finishes with no problem.
Version (include the version you are using, if applicable):
25B
Code Snippet (add any code snippets that support your topic, if applicable):