The scheduling method can't be set to value NO_SCHEDULING if the allow explosion indicator is Y
Summary:
We have an external planning system that creates work orders with its own planned start and completion dates. We use FBDI to send these work orders to Oracle. However, we get this error: "The scheduling method can't be set to value NO_SCHEDULING if the allow explosion indicator is set to yes."
If we don’t set the Allow Explosion flag to "N", we don’t get the operation details.
Is there a way to keep the start and completion dates from the external system and also set the Allow Explosion flag so the operations are included?
Content (please ensure you mask any confidential information):