How to Configure GOP to Use Business Days Instead of Calendar Days for SAD Date Calculation
Hi Experts,
Currently, based on our GOP (Global Order Promising) configurations, the SAD (Scheduled Arrival Date) is calculated using calendar days rather than business days.
For example, if we have an item with a lead time of 10 days and place an order on Monday, 13th October 2025, GOP calculates the promise date as 22nd October—counting 10 calendar days.
We would like the GOP to consider only business days (excluding weekends and holidays) when calculating the promise date.
Could you please advise how we can configure GOP to achieve this?
Thanks in advance!
Sam,