Maintenance Program – Need Help Aligning Weekly/Monthly/Yearly Cycle to 365 Days

edited 8:54AM in Maintenance

Summary:

Unable to Configure Weekly, Monthly, and Quarterly Maintenance with Suppression Logic Using Day Interval

Description:

We are trying to configure a Maintenance Program in Oracle Fusion Cloud Maintenance but are unable to meet the business requirement due to base interval limitations and forecast alignment behavior.

Business Requirement

We need to configure:

  • One Work Requirement
  • Three Work Definitions under the same Work Requirement:
    • Weekly Work Definition
    • Monthly Work Definition
    • Quarterly Work Definition

Expected Functional Behavior

  1. Weekly Work Definition
    • Should generate every 7 days.
    • When Monthly or Quarterly activity falls in the same period, the weekly work should be suppressed accordingly.
    • However, weekly generation should resume normally after suppression.