schedule ship date is not right when the supply consist of onhand and PO for an order line
Summary:
the schedule ship date suggested is a few days later than the PO inbound
Content (please ensure you mask any confidential information):
request date is 14 Feb, Ordered quantity is 300000, onhand is 212860;
The proposed PO on boarding day is 26 Feb considering the pre and processing days
The schedule ship date is 1 Mar, why it is later than 26 Feb? There is no pick and pack lead time, the calendar is 7x7 24h
Version (include the version you are using, if applicable):
Code Snippet (add any code snippets that support your topic, if applicable):