schedule ship date is not right when the supply consist of onhand and PO for an order line

Summary:

the schedule ship date suggested is a few days later than the PO inbound

Content (please ensure you mask any confidential information):

request date is 14 Feb, Ordered quantity is 300000, onhand is 212860;

The proposed PO on boarding day is 26 Feb considering the pre and processing days

The schedule ship date is 1 Mar, why it is later than 26 Feb? There is no pick and pack lead time, the calendar is 7x7 24h