Supplier allocation percentage does not follow the sourcing rule set.
Summary:
Hello Team,
A sourcing rule is defined for an item XYZ to
-transfer from an org A; allocation percent is 85 and Rank is 1.
-Buy from a supplier B; allocation percent is 15 and Rank is 1.
But after plan run, the planned orders suggested are only for the supplier B not for the org A.
Upon checking, the total open supply for source org A is 2398 whereas the and for supplier B is 7072. Is this the reason?