Category 162
Discussion List
-
Query related to existing SR 3-33067915011: Change-over overlaps with delaysWe could see that 24A feature has come thru as "CONSIDER RESOURCE CALENDARS FOR PRODUCTION CHANGEOVERS" related to this issue. Does this fix the issue by honoring manufa…Uttam Eitha 51 views 4 comments 0 points Most recent by Uttam Eitha Supply Chain Planning and Collaboration -
Could you explain the assigment about the stock on hand on the finished product please in planning?I would like to know the assigment of the PF stock. I don't understand why the stock is link to the sales order 23000341 - Requested ship date : 14/11/2023. that's not t…C:BRANCHI 12 views 5 comments 0 points Most recent by Thierry Lamote Supply Chain Planning and Collaboration -
How the need-by date for planned order (make) is calculated?In "Supplies and Demands", where does the system retrieve the need by date information from? Is it from the work definition?C:BRANCHI 66 views 6 comments 0 points Most recent by Thierry Lamote Supply Chain Planning and Collaboration -
Demand Priority Rule is neither considering the Item Categories as an Attribute nor to add DFF on UIFor Constrained Supply Planning, the system is not allowing to attach Item Categories as a demand priority attribute. The requirement is to have Rank 1 for A Class Items…SidSaxena 37 views 3 comments 0 points Most recent by Prateek_16-Oracle Supply Chain Planning and Collaboration -
Custom measures are not acting as Causal factors for ForecastingSummary: I have defined a custom measure and would like to use it as Causal factor for forecasting. I have established a negative correlation for the shipments history w… -
Can the safety stock be calculated for Model Item ?Summary: We have business scenario where we want to generate safety stock for ATO model and then based on the generated safty stock values for Model item supply plan sho…Sumit_99 25 views 4 comments 0 points Most recent by Sumit_99 Supply Chain Planning and Collaboration -
Is there any report that lists all planned orders for which PR is not generated?Summary: Is there any report that lists all planned orders for which PR is not generated? Version (include the version you are using, if applicable): 23DRaju Pachigolla 21 views 5 comments 0 points Most recent by Raju Pachigolla Supply Chain Planning and Collaboration -
release plan ESS job is not picking items marked for release in supply planningSummary: Content (please ensure you mask any confidential information): Version (include the version you are using, if applicable): Code Snippet (add any code snippets t…SARTHAK GOSWAMI 4 views 1 comment 0 points Most recent by Prateek_16-Oracle Supply Chain Planning and Collaboration -
selling price in plan inputs and demand plan not populating under items tableSummary: how to get this populated, we ran collection for price lists, plan options contain price list as primary. Content (please ensure you mask any confidential infor…SARTHAK GOSWAMI 12 views 1 comment 0 points Most recent by Prateek_16-Oracle Supply Chain Planning and Collaboration -
How to purge vcs_collab_details_int tableSummary: Content (please ensure you mask any confidential information): Version (include the version you are using, if applicable): Code Snippet (add any code snippets t…SARTHAK GOSWAMI 11 views 1 comment 0 points Most recent by Prateek_16-Oracle Supply Chain Planning and Collaboration -
Transportation Capacity in Supply PlanningSummary: Have you modeled Transportation Capacity in Supply Planning or Sales and Operations Planning? We understand that it is not supported directly by Supply Planning…RakeshOracle-Oracle 43 views 5 comments 0 points Most recent by RakeshOracle-Oracle Supply Chain Planning and Collaboration
-
Custom Measure Calculation ErrorSummary: Created Two custom Measure: 1. Promotion Percentage 2. Adjusted Promotion Percentage Forecast we are expecting for Customer Measure Adjusted Promotion Percentag…DineshApps 26 views 3 comments 0 points Most recent by Prateek_16-Oracle Supply Chain Planning and Collaboration -
Calculate Lead Times and Roll Up Cumulative Lead TimesIn Work Definition, time required to make 1 unit of the Make Item / finished good is 20 minutes. Resource is working on a shift ( 8 hours) . After running "Calculate Lea…Rithu 34 views 5 comments 0 points Most recent by Thierry Lamote Supply Chain Planning and Collaboration -
How can we add the same component with different effective date in the Itemstructure table in simsetSummary: How can we add the same component with different effective date (Component Start and end date)in the Item structure table in simulation set. Content (please ens…Priya.George 42 views 7 comments 0 points Most recent by Cherry Bruns-Oracle Supply Chain Planning and Collaboration -
sales order uploaded via FBDi appear in plan inputs but not in supply planSummary: FBDI used- SCPsalesorderimportTemplate Content (please ensure you mask any confidential information): Version (include the version you are using, if applicable)…SARTHAK GOSWAMI 41 views 6 comments 0 points Most recent by Thierry Lamote Supply Chain Planning and Collaboration -
Why in planning pegging analysis the date is not coherent with the date in supplies and demand plan?Why in planning pegging analysis the date is not coherent with the date in supplies and demand plan? indeed in pegging analysis we can just see the demand date only for …C:BRANCHI 22 views 2 comments 0 points Most recent by C:BRANCHI Supply Chain Planning and Collaboration -
calculated measure not giving the resultSummary: we are using Nvl expression in measure. it sums up the measure as following: nvl(measure1, 0) + nvl(measure2, 0) + nvl(measure3, 0) + nvl(measure4, 0) + nvl(mea…SARTHAK GOSWAMI 22 views 2 comments 0 points Most recent by Santhamathi Mathimugam-Oracle Supply Chain Planning and Collaboration -
what is logic used by forecast engine to remove history outlier?Summary: Forecast engine removes outlier from historical data to minimize forecast error. User guide only have details of parameters to handle sensitivity of detection a…Priyank R Khare 68 views 2 comments 0 points Most recent by Santosh V-Oracle Supply Chain Planning and Collaboration -
Contract manufacturer one to one mapping clarificationSummary: As per Oracle note Master KM: Contract Manufacturing in Oracle Cloud (Setup, Functional Flow, FAQ, Troubleshooting) (Doc ID 2670566.1) “..........Contract Manuf…Nirabh Nayan 36 views 4 comments 0 points Most recent by Nirabh Nayan Supply Chain Planning and Collaboration -
if supply plan setup has compression tolerance days =250 while planned orders are transfer orderSummary: what happens if supply plan setup has compression tolerance days =250 while planned orders are transfer order with no compression days Content (please ensure yo…SARTHAK GOSWAMI 22 views 8 comments 0 points Most recent by Thierry Lamote Supply Chain Planning and Collaboration -
Time Phased Safety Stock levels in S&OPSummary: Are Time Phased Safety Stock Levels supported in S&OP Content (please ensure you mask any confidential information): Are Time Phased Safety Stock Levels support…Avinash Erande 42 views 4 comments 0 points Most recent by Sebastian Thomas Supply Chain Planning and Collaboration -
Split sourcing rule not considered by Supply Plan while creating planned ordersPlan type = constrained plan Item type = Buy item In plan options, ''Use alternate suppliers and source organizations'' is enabled under Constraints and Decision Rules. … -
Does Supply chain command center comes with the licensing of Supply chain Collaboration cloudSummary: Does Supply chain command center comes with the licensing of Supply chain Collaboration cloud... What is the License Hierarchy for the same in order to get Supp…Vignesh S R 102 views 3 comments 0 points Most recent by Victor Martin Supply Chain Planning and Collaboration -
Price listsSummary: Consolidation of price lists for SCP Content (please ensure you mask any confidential information):We have multiple business units with unique price lists and w…Brian Hicks 42 views 4 comments 0 points Most recent by F_Suarez Supply Chain Planning and Collaboration -
External Forecast FBDI does not support the Date Format MM/DD/YYYYSummary: External Forecast FBDI does not support the Date Format MM/DD/YYYY Content (please ensure you mask any confidential information): The date format of the column …SCMLEAD_AA 22 views 4 comments 0 points Most recent by Santosh V-Oracle Supply Chain Planning and Collaboration -
Resource utilization smootheningSummary: Hi, We are using the resource plan to plan out the capacity of our laborers. But in the resource plan we see that the resource utilization is extremely high in …Thushara Unnikrishnan 42 views 5 comments 0 points Most recent by Prateek_16-Oracle Supply Chain Planning and Collaboration -
Is there an equivalent of "Level Methods" of Demantra in Demand ManagementSummary: Experts, In Demantra, there was the functionality of defining Methods at a dimension level which can potentially contain some custom logic. Is there an equivale…Sudeep VS 53 views 2 comments 1 point Most recent by NareshT Supply Chain Planning and Collaboration -
Difference in processing lead time defined in PIM and manufacturing time defined in work definitionSummary: For a make item, processing lead time defined in PIM screen is defined in days only whereas, processing time defined in work definition can be defined in hours/…AishwarSri 75 views 2 comments 0 points Most recent by NareshT Supply Chain Planning and Collaboration -
can we split work order quantities in Product Scheduling Planning Module in Oracle fusion?Summary: We need to split work order quantities based on Machine A, Machine B. Is it possible to achieve this in Production scheduling? Content (please ensure you mask a…Vatsala Bharadwaj-Oracle 36 views 1 comment 0 points Most recent by M. Bolsinger-Oracle Supply Chain Planning and Collaboration -
Collect Planning Data Re-plans 'Firm' Planned OrdersSummary: Planners 'firm' planned orders setting the 'firm date' and the 'firm quantity'. Planning is scheduled to run three times a day, setup to 'complete refresh'. 'Fi…Jorge Mak 31 views 6 comments 0 points Most recent by Jorge Mak Supply Chain Planning and Collaboration