To ensure that questions get required attention from community members and are NOT left unanswered, it’s important for the author to indicate (by selecting “Yes” or “No” when prompted) whether the question was answered. (newly added) Please note that it is also important to respond to EACH comment your question receives. Your Yes or No response ensures an accurate status for your question.
For more information, please refer to this announcement explaining best practices for getting answers to questions.
For more information, please refer to this announcement explaining best practices for getting answers to questions.
TCC scripts won't run after upgrading from 14A to 15A
Summary
Bat files won't run after upgrading TCC from 14A to 15A.2.0.20.Content
Bat files won't run after upgrading TCC from 14A to 15A.2.0.20. After the upgrade was finished,
I manually ran 9 integrations within TCC (Orgs, Locations, Job Fields, Departments, etc.) running both
the initial and ongoing from TCC and they all ran successfully. However these same imports
(ongoing only) failed when running from a batch script.
Getting this error - Description: A general internal error occurred.
Reason: Data Storage Manager not initialized.
The error occurred in the following step: Net Change Computation (Pre) The corresponding code for this error in version 1.0 would have been: -1 The error was caused by the following exception:
2