Sales and Operations Planning Exceptions
Summary
Details of Lead Time Compression ExceptionContent
Hello,
The Sales and Operations Planning Engine generates Lead Time Compression exceptions.
What all parameters are considered (Pre processing , Post processing etc) when calculating the lead times for both Buy and Make items?
Also, this exception only shows that lead time compression is for example : 12 days. Is there a table or a report that can help users understand what is causing this 12 days delay ( Supplier lead time for a component buy item or manufacturing lead time of a Make item) or anything else so that suitable action can be taken to mitigate this issue.