How to allow Order Promising by allowing overloads to the resources- B2B scenario
Summary
Need to promise on an earlier date than what GOP is suggesting. Want to GOP to consider the overload while promising the subsequent ordersContent
In my client’s organization, the manufacturing is mostly custom, based on client requirements with shorter lead time – generally gets delivery between 1-7 days. We’ve modelled this in the back to back flow. And at times, production has flexibility to accommodate more work orders – due to fewer changeovers / additional operators etc.
I am thinking of giving them the option of overriding SSD, when they can accommodate more workers. And I’ve got the Pre-transformation Rule to set SSD based on a Date (have the Override Schedule Flag = Yes).