Need to model in extra day in the lead time to provide allowance for packaging etc. without impactin

Received Response
17
Views
5
Comments
edited Jan 9, 2019 7:00AM in Order Management 5 comments

Summary

Need to model in extra day in the lead time to provide allowance for packaging etc. without impacting the resource load

Content

Hi, 

The client requires an  extra day post manufacturing, for packing etc, to ship the goods out. 

This extra day needs to be factored in while promising the delivery to the customer. What is the best way to model this so GOP can add an extra day when coming up with the SSD, at the time time this extra day should not consume resource capacity, 

If we use Fixed Lead time in PIM, will that work. Does the FLT consume resource capacity? 