Need to check the work definition that are to be forecasted through Gantt chart
Summary
Unable to check what are the work definition available on a day to be created in a work order.Content
Hi,
We have created a work requirement with a few work definitions which get due at different cycle intervals.
when we generate the gantt chart forecast we are unable to see what work definition gets created in the work order before hand.
Scenario
Maintenance program = Crane Services (Start date 11-Jan-2020)
work requirement = Crane 2
forecast using a cycle = Enabled
number of interval per cycle = 365
work definition 1 due at cycle interval = 30
work definition 2 due at cycle interval =60
work definition 3 due at cycle interval =5
2