Summary

Unable to check what are the work definition available on a day to be created in a work order.

Content

Hi,

We have created a work requirement with a few work definitions which get due at different cycle intervals.

when we generate the gantt chart forecast we are unable to see what work definition gets created in the work order before hand.

 

Scenario

Maintenance program         =       Crane Services (Start date 11-Jan-2020) 

work requirement                  =     Crane 2

 forecast using a cycle          =     Enabled

number of interval per cycle =     365

 work definition 1 due at cycle interval = 30

work definition 2 due at cycle interval  =60

work definition 3 due at cycle interval  =5