Preparer initiated change order from Self Service Procurement

Received Response
32
Views
4
Comments
edited May 4, 2020 10:38AM in Self Service Procurement 4 comments

Summary

Preparer initiated change order from Self Service Procurement to update and add new line

Content

The question is regarding the PO change order which is initiated by the Preparer instead of the Requester mentioned in the requisition.The Preparer (front desk) raises a requisition for $1000 (venue hire) on behalf of the requester (Manager) which gets converted into PO $1000.The preparer then changes order using Edit Order to update the existing line of $1000 to $1500 and adds a new line for $600 (catering) with all the details including the charge account,requester (Manager) same as in the previous line.

The preparer initiated change order is approved and PO is revised with changes.Noticed there is no requisition linked to the new line 2.