Reallocate Project Details on Receipt
Summary
Is there a way or work around to reallocate project details on a receipt? Client want's to avoid doing a change orderContent
Scenario
Building a road.
WBS looks like….
1.0.0 Prelims…..
2.0.0 First bit of road
2.0.0.1 Road
2.0.0.1.1Tarmac
2.0.0.1.2Lights
2.1.0.1 Bridge
2.1.0.1 Foundations
2.1.0.2 Structure
3.0.0 Second bit of road
3.0.0 Road
3.0.0.1.1 Tarmac
3.0.0.1.2 Lights
3.1.0 Bridge 2
3.1.0.1.1 Foundations
3.1.0.1.2 Structure
Raise a PO for 10,000 M3 of concrete
Distribute it 50/50 between the task Foundation for Bridge 1 and Foundations for bridge 2
A lorry turns up with 1000M3 of concrete at a price of £10 per m3
It all gets poured into the hole for Bridge 1 (Bridge 2 not ready for operational reasons)