Mid point scheduling of Work Orders
Summary
Mid point scheduling of Work Orders without impacting the start & end dates of prior operationsContent
For an unconstrained planning scenario , is it possible to do a midpoint scheduling of a work order without impacting the start & end dates of prior operations ?
Example : WO # TNK001 has 3 operations where each operation consumes 8 hours each . After the WO is released , the Start & completion dates get populated automatically for each operation based on the WO start date & Resource usage value of respective operations
While the 1st operation is in-process , the prod engg expects a delay in the completion of 2nd operation and extends the scheduled completion date of operation # 02. Will this change result in