Thank you for supporting the Cloud Customer Connect Community in 2024. It's a gift to work with you!

Look back
You're almost there! Please answer a few more questions for access to the Applications content. Complete registration
Interested in joining? Complete your registration by providing Areas of Interest here. Register
Get Started with Redwood for Oracle Cloud HCM   Begin Now
To ensure that questions get required attention from community members and are NOT left unanswered, it’s important for the author to indicate (by selecting “Yes” or “No” when prompted) whether the question was answered. (newly added) Please note that it is also important to respond to EACH comment your question receives. Your Yes or No response ensures an accurate status for your question.

For more information, please refer to this announcement explaining best practices for getting answers to questions.

Prorate shift allowance in payroll based on absence duration.

Summary:

Need guidance on how to prorate shift allowance in payroll based on absence duration.

Content (required):

Hello EveryoneThere is a requirement to sum up the absences taken by an employee in a month and prorate the Shift allowance based on the total absence duration.As an example :

Shift allowance/month - $900

Absence start and end date:- 01-Nov-2021 - 03-Nov-2021 and 20-Nov-2021 - 21-Nov-2021

Total Absence Duration - 5 days

Shift allowance paid for Nov'21 = 900 - 150(5 days allowance) = 750I am able to achieve it using a table value set if there is a single absence record in a month , but it does not work wherever there are multiple absence records.Any guidance or FF sample will be greatly appreciated.